Building Regulations New Approved Document E came into force on 1st July 2003 with the introduction of pre-completion testing (PCT) for sound insulation as a means of demonstrating compliance, and as from 1st July 2004 the use of Robust Details (RD) in new build has been accepted as an alternative to pre-completion testing.
Requirements E1, E2 and E3 of Document E apply to the sound insulation of any type of conversion or new build used as a dwelling including; houses, apartments, hostel rooms, hotels, boarding houses, halls of residence and residential homes. Requirement E4 applies to acoustic conditions in schools.
Performance standards are given for each requirement, as follows.
Airborne sound insulation Sound insulation (Minimum values) |
Impact Sound insulation (Maximum values) |
|
| Purpose built dwelling - houses and flats | ||
| Walls | 45 |
- |
| Floors & Stairs | 45 |
62 |
| Dwelling - houses and flats formed by material change of use | ||
| Walls | 43 |
- |
| Floors & Stairs | 43 |
64 |
Airborne sound insulation Sound insulation (Minimum values) |
Impact Sound insulation (Maximum values) |
|
| Purpose built dwelling - houses and flats | ||
| Walls | 43 |
- |
| Floors & Stairs | 45 |
62 |
| Dwelling - houses and flats formed by material change of use | ||
| Walls | 43 |
- |
| Floors & Stairs | 43 |
64 |
Airborne sound insulation (Minimum values) |
||
| Walls | 40 |
|
| Floors | 40 |
For further information on Approved Document E visit www.communities.gov.uk or www.planningportal.gov.uk